lsg solutions logo

Khobi 2 HPP

CLIENT: GIG ENERGY
AREA: 6.6 KM TUNNEL
COMPLETION DATE: SEPTEMBER 2023
SCOPE: CONSTRUCTION SUPERVISION AND QUALITY CONTROL

ABOUT PROJECT: A medium-sized hydropower plant is being built in the Samegrelo region of Georgia, according to the order of the Georgian Investment Group—Energy (GIGE). The installed capacity of the HPP is 46 MW. The 6.6 km long tunnel was drilled with modern technology by TBM (Tunnel Boring Machine). The owner’s engineering scope is under Multiconsult UK, which together with the LSG Solutions local team is responsible for monitoring the work and ensuring that the construction is carried out with quality.

Khobi-1024x1024
310629484_425055283086914_6889772258761547727_n
310489849_658896242217629_1806070730099804104_n

© All rights Reserved - Lsg Solutions 2023